New Metro-North schedule for White Plains station, track improvements

Facebook
Twitter
LinkedIn
Email
Print

NEW YORK – Metro-North
Railroad will implement new Harlem Line schedules and minor changes to
Hudson Line schedules effective Sunday, March 18.

The new schedules allow Metro-North to begin an extensive three-year project
to transform the White Plains station, making it safer, brighter, cleaner
and easier to navigate.

The scheduled may be viewed at www.MTA.info.

The general scope of the $94 million investment in the station includes
improved entrances, new signage, platforms, energy efficient LED lighting,
benches with USB charges, station dashboards and totems to provide access
to information, upgrades to customer restrooms, Wi-Fi and cell connectivity.
The state’s interior will get a major makeover with new wall panels,
ceiling tiles and fixtures.

The White Plains Station is located in two-track territory. For the duration
of the project, one of the two tracks will be removed from service during
off-peak and weekend hours to allow construction crews to have access
to the platforms and to perform their work safely. The construction will
not affect peak-hour weekday service and peak-hour schedules remain unchanged,
MTA officials said.

During the first phase of improvements to the White Plains Station, Metro-North
crews will also be rehabilitating track between Scarsdale and Hartsdale.
That work lays the foundation for plans to begin refurbishing both stations
next year and requires off-peak single-tracking between Scarsdale and
Hartsdale.

Between Brewster and Southeast, crews will replace switches. That work
will require single-tracking on weekends for three months for some 10
miles of track between Goldens Bridge and Southeast stations. To accommodate
that track work, off-peak service will be reduced from half-hourly to
hourly. Off-peak half-hourly service will return with the fall 2018 schedule.

  