NYACK – Clearing work will begin next to the south side of the southbound Thruway in South Nyack on Monday in preparation for installation of a retaining wall and permanent, sound-absorbing concrete noise barrier in late spring.
Crews will also continue working on the new Tappan Zee Bridge’s landings on the Rockland and Westchester shorelines.
Ice buildup on the Hudson continues to limit operations at the project. Tappan Zee Constructors has included a two-month winter shutdown in its schedule to account for winter weather.
Weather permitting construction will continue in the river as crews place the foundations of the new bridge.